Jilin City Hengyuan Paper Industry Co., Ltd. annual output of 150,000 tons of paper and 300,000 tons of pulp expansion renovation project completion acceptance of fire record spot check results notice

来源:   时间: 2023-05-25 13:18

Jilin City Hengyuan Paper Co., LTD. Annual production15Tons of paper and30Notice of notice of the result of random inspection for the fire record of the completion acceptance of the project


 Jigao residential construction completed(R/□复)字〔2023〕第01

Jilin City Hengyuan Paper Co., LTD2023523diurnal年产15Tons of paper and3010,000-ton pulping capacity expansion Project (Pulping workshop)(地址:Songjiang North Road, Xiushui Industrial Park, Jilin High-tech Zone2088,Building area:4830Square meters;Building height:22.1Meters;Number of building floors:Aboveground region2Layer;Nature of use:厂房。According to the provisions of the relevant laws, regulations and rules of the People's Republic of China Fire Protection Law and the Jilin Province Fire Protection Design Review and Acceptance Management Measures, the project is identified as the object of random inspection in accordance with the method of random selection of inspection objects。

2023525日,我□委(R局)The above items were carried out according to lawR/□复查。After the review of the filing application materials and the on-site inspection and testing of the project, the on-site assessment of the above project fire completion acceptance record is unqualified。The main problems are as follows:

First, the fire spacing between the pulp workshop and the raw material canopy is inconsistent with the planning (planning15Meters, site9.3米);

Second, the southern building of the pulp workshop is not planned, built outside the planning red line, and the factory lacks an entrance and exit;

3. Two outdoor fire hydrants around the pulping workshop have not been constructed;

4. The relevant data of the fire water supply system is inconsistent with the description of the design document;(For example: hydrant pump design flow rate60L/SThe actual scene is30L/SThe fire pool design document is800m³, the scene is600m3. The fire stabilizing pump is not set according to the design requirements, the low pressure pressure switch is not set, the two fire pumps share the same outlet pipe, the on-site fire pump is always in working condition and the fire pump leaks;Fire pump control cabinet and other problems were not found at the scene)

Fifth, the pulping workshop high-voltage power distribution room to the outdoor safety exit using rolling shutter doors, not according to the design requirements of the fire door。

Jilin City Hengyuan Paper Co., Ltd. will rectify the above problems, and report the rectification to us (RBureau) request review。The project shall not be put into use without passing the inspection;If it has been used, it should be stopped immediately。

 


Jilin high-tech Industrial Development Zone housing and urban-rural construction Bureau

2023525